5 Boro Complex and Garage Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the parking lot at the 5 Boro Complex and Garage on Randall's Island.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: December 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Adjusted Completion Date: September 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
20 Bronx Shore Road

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/22/2019