5 Boro Complex and Garage Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    11% complete

This project will reconstruct the parking lot at the 5 Boro Complex and Garage on Randall's Island.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: December 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $1,685,000
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
20 Bronx Shore Road

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/29/2020