Newport Playground Comfort Station Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the comfort station in Newport Playground.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: April 2016
Projected Completion Date:
March 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
June 2018
Construction
Start Date: February 2019
Projected Completion Date:
August 2020
Completion
Date:
November 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Newport Playground
, Brooklyn
Riverdale Avenue between Osborn Street and Thatford Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 06/30/2022