Newport Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Newport Playground.
Project Timeline
Design
Start Date: March 2016
Projected Completion Date:
April 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
May 2018
Construction
Start Date: June 2018
Projected Completion Date:
September 2019
Completion
Date:
July 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Newport Playground
, Brooklyn
Riverdale Avenue between Osborn Street and Thatford Avenue, adjacent to P.S. 41
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 06/30/2022