Newport Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Newport Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $3,389,000
Funding Source: Mayoral

Location

Newport Playground , Brooklyn
Riverdale Avenue between Osborn Street and Thatford Avenue, adjacent to P.S. 41

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/15/2018