MacArthur Park Multi-Purpose Ballfield and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will reconstruct the existing ballfields, basketball courts, and sports lighting, and improve the edges and entrances at MacArthur Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: October 2020
Adjusted Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $11,090,000
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Gen. Douglas MacArthur Park , Staten Island
Jefferson Street between Dongan Hills Avenue and Seaver Avenue

 