MacArthur Park Multi-Purpose Ballfield and Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the existing ballfields, basketball courts, and sports lighting, and improve the edges and entrances at MacArthur Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
February 2018
Procurement
Start Date: February 2018
Projected Completion Date:
November 2018
Completion
Date:
March 2019
Construction
Start Date: April 2019
Projected Completion Date:
October 2020
Completion
Date:
May 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Gen. Douglas MacArthur Park
, Staten Island
Jefferson Street between Dongan Hills Avenue and Seaver Avenue
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 07/01/2022