MacArthur Park Multi-Purpose Ballfield and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the existing ballfields, basketball courts, and sports lighting, and improve the edges and entrances at MacArthur Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Gen. Douglas MacArthur Park , Staten Island
Jefferson Street between Dongan Hills Avenue and Seaver Avenue

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 06/19/2018