Arden Woods Trailhead Parking Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will construct an off-street parking lot and trailhead at Arden Woods.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: March 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $1,652,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Arden Woods , Staten Island
Arden Avenue between Kyle Court and Forest Green

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 12/08/2021