Arden Heights Woods Trailhead Parking Construction and Trail Improvements

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct an off-street parking lot and trail head and improve trails in Arden Heights Woods.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: March 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Adjusted Completion Date: March 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Arden Woods , Staten Island
Arden Avenue between Kyle Court and Forest Green

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/08/2019