Arden Heights Woods Trailhead Parking Construction and Trail Improvements

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct an off-street parking lot and trail head and improve trails in Arden Heights Woods.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: March 2018
Adjusted Completion Date: December 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Arden Woods , Staten Island
Arden Road between Kyle Court and Forest Green

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 10/15/2018