NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Riverside Park Joan of Arc Island Reconstruction and Adult Fitness Equipment Installation

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the concrete stairs and asphalt paths in the area adjacent to the Joan of Arc monument. between West 91st Street and West 95th Street, and install adult fitness equipment, bike racks and benches adjacent to the basketball courts at Neufeld Playground near West 76th Street in Riverside Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Source: City Council

Location

Riverside Park, Manhattan
Riverside Drive from W 91st Street to W 95th Street and at W 76th Street, south of Neufeld Playground

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?