NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Flushing Meadows Corona Park Pool Emergency Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at the Flushing Meadows Corona Park Pool.

Project Timeline

Design

Start Date: November 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: July 2017

Construction

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: October 2017

Understand how we build parks.

Funding

Total Funding: $944,000

Location

Flushing Meadows Corona Park, Queens
131-04 Meridian Road, Flushing, NY 11368

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?