Travers Park Tot Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    52% complete

The project will reconstruct the tot lot in Travers Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Adjusted Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Source: Borough President

Location

Travers Park , Queens
78th Street between Northern Boulevard and 34th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/07/2020