Marcus Garvey Park Pelham Fritz Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entrance lobby and retaining walls at Pelham Fritz Recreation Center in Marcus Garvey Park.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: March 2020

Construction

Start Date: November 2020
Projected Completion Date: May 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Sources:
  • Mayoral
  • City Council

Location

Marcus Garvey Park , Manhattan
18 Mt. Morris Park West at West 122nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/25/2022