Marcus Garvey Park Pelham Fritz Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the entrance lobby and retaining walls at Pelham Fritz Recreation Center in Marcus Garvey Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: March 2020

Construction

Start Date: November 2020
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,001,000
Funding Sources:
  • Mayoral
  • City Council

Location

Marcus Garvey Park , Manhattan
18 Mt. Morris Park West at West 122nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/28/2020