Marcus Garvey Park Pelham Fritz Recreation Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the entrance lobby and retaining walls at Pelham Fritz Recreation Center in Marcus Garvey Park.
Project Timeline
Design
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
March 2020
Construction
Start Date: November 2020
Projected Completion Date:
May 2022
Completion
Date:
April 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Marcus Garvey Park
, Manhattan
18 Mt. Morris Park West at West 122nd Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 05/25/2022