Freshkills South Park Construction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct synthetic turf athletic fields, a comfort station, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands at Freshkills Park.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Freshkills Park , Staten Island
West Shore Expressway, Arden Avenue, Arthur Kill Road

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project