Freshkills South Park Construction

  • Design
    5 % complete 
  • Procurement
     
  • Construction
     

This project will construct multipurpose athletic fields and an adjacent comfort station; construct a playground and parking lot with associated landscaping and stormwater management; create a multi-use pedestrian path system; restore important ecological assets including woodlands and wetlands; and provide new site amenities including benches, signage, fencing and lighting.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayor

Location

Freshkills Park , Staten Island
Bounded by the West Shore Expressway, Arden Avenue and Arthur Kill road, in the South Park section of Freshkills Park

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 05/25/2017

Was this information helpful?