Nelson Playground Bleachers Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the bleachers at Nelson Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: February 2017
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $354,000
Funding Source: City Council

Location

Nelson Playground , Bronx
West 166th Street between Woodycrest Avenue and Nelson Avenue

 

Project Staff

Project Liaison: Michelle Martell