Prospect Park Vale of Cashmere Path Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct two sections of pathways in the Vale of Cashmere section of Prospect Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Adjusted Completion Date: January 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Prospect Park , Brooklyn
From the north side of the Endale Arch to the newly reconstructed path near the Zucker Natural Exploration area, and from Flatbush Avenue to the same reconstructed path

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/22/2019