Prospect Park Vale of Cashmere Path Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct two sections of pathways in the Vale of Cashmere section of Prospect Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Adjusted Completion Date: January 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Prospect Park , Brooklyn
From the north side of the Endale Arch to the newly reconstructed path near the Zucker Natural Exploration area, and from Flatbush Avenue to the same reconstructed path

 