Lt. Federico Narvaez Tot Lot Reconstruction
-
100% complete
-
100% complete
-
70% complete
This project will construct new play equipment for 2-5 years old, benches, fencing, drainage and water supply systems and plantings in Lt. Federico Narvaez Tot Lot.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
November 2017
Procurement
Start Date: November 2017
Projected Completion Date:
August 2018
Completion
Date:
December 2019
Construction
Start Date: March 2020
Projected Completion Date:
March 2021
Adjusted Completion
Date:
May 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Lt. Federico Narvaez Tot Lot
, Brooklyn
Argyle Road between Cortelyou Road and Dorchester Road
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/26/2021