Lt. Federico Narvaez Tot Lot Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct new play equipment for 2-5 years old, benches, fencing, drainage and water supply systems and plantings in Lt. Federico Narvaez Tot Lot.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Adjusted Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Lt. Federico Narvaez Tot Lot , Brooklyn
Argyle Road between Cortelyou Road and Dorchester Road

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/14/2018