Fort Greene Park Plaza and Pavement Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the oval plaza, lower plaza and sidewalk along Myrtle Avenue and staircases at St. Edwards Street and Willoughby Street and at DeKalb Avenue and Washington Park. The work will include pavement, drainage and handrail reconstruction, and new plantings, water features, lighting, seating, barbecues, and adult fitness equipment.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: November 2016
Projected Completion Date:
November 2017
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Adjusted Completion
Date:
November 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Fort Greene Park
, Brooklyn
Myrtle Avenue, De Kalb Avenue between Washington Park and St. Edwards Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/25/2021