Homecrest Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the children's play area in Homecrest Playground, including the spray shower, play equipment, paving, site furniture, landscaping and utilities.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,897,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Homecrest Playground , Brooklyn
Williams Court, East 14th Street, Homecrest Avenue, Shore Parkway

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/03/2020