East River Esplanade Reconstruction, East 68th-70th Streets

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will reconstruct the East River Esplanade from East 68th Street to East 70th Street.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $2,046,000
Funding Sources:
  • Mayoral
  • City Council

Location

East River Walk , Manhattan
between the East River and FDR Drive, East 68th Street to East 70th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/30/2021

Was this information helpful?