McKinley Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the playground and spray shower, including fencing, paving, curbs, safety surfacing, benches, lighting, play equipment, plantings, and trees at McKinley Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Adjusted Completion Date: February 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

McKinley Playground , Manhattan
East 3rd Street, East 4th Street, Avenue A, 1st Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/12/2019