McKinley Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    13% complete

This project will reconstruct the playground and spray shower, including fencing, paving, curbs, safety surfacing, benches, lighting, play equipment, plantings, and trees at McKinley Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,995,000
Funding Sources:
  • Borough President
  • City Council

Location

McKinley Playground , Manhattan
East 3rd Street, East 4th Street, Avenue A, 1st Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/25/2020