NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

LaGuardia Playground Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct LaGuardia Playground in Brooklyn.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Adjusted Completion Date: June 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

La Guardia Playground , Brooklyn
Roebling Street, Havemeyer Street, South 4th Street and South 5th Street.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/22/2018

Was this information helpful?