DeWitt Clinton Park Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the staircases in DeWitt Clinton Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

De Witt Clinton Park , Manhattan
11th Avenue, 12th Avenue, West 52nd Street, West 54th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/17/2019