Columbus Park Mulberry Street Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the Mulberry Street entrance at Columbus Park.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Columbus Park , Manhattan
Mulberry Street between Bayard and Mosco Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/14/2019