Columbus Park Mulberry Street Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the Mulberry Street entrance at Columbus Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $467,000
Funding Sources:
  • Mayoral
  • City Council

Location

Columbus Park , Manhattan
Mulberry Street between Bayard and Mosco Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/19/2019