Weeksville Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Weeksville Playground with new play equipment, seating and planting beds.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,176,000
Funding Source: Mayoral

Location

Weeksville Playground , Brooklyn
Howard Avenue between Atlantic Avenue and Herkimer Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2019