Abraham Lincoln Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    27% complete

This project will reconstruct Abraham Lincoln Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: January 2020

Construction

Start Date: March 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $9,395,000
Funding Source: Mayoral

Location

Abraham Lincoln Playground , Manhattan
Fifth Avenue and East 135th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020