Sternberg Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct the synthetic turf field and construct new sports lighting at the basketball courts at Sternberg Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: February 2020

Construction

Start Date: October 2020
Projected Completion Date: October 2021

Understand how we build parks.

Funding

Total Funding: $3,100,000
Funding Source: City Council

Location

Sternberg Park , Brooklyn
Montrose Avenue, Boerum Street, Lorimer Street, Leonard Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020