Garrison Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct the seating area and playground at Garrison Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $4,386,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Garrison Playground , Bronx
Grand Concourse between East 144th Street and East 149th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/15/2018