Playground 134 Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct or remove existing handball courts and construct new basketball courts, play equipment, a skate park, adult fitness equipment, a spray shower, swings, synthetic turf, safety surface, fencing, screening, retaining walls, ramps, seating, sidewalks, plantings, drainage, and water supply systems at Playground 134.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: November 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • State

Location

Playground One Thirty Four CXXXIV , Bronx
Located at E. 133 St. and Bruckner Blvd. bet. St Ann's Pl. and Cypress Ave. Borough of the Bronx.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/15/2018