Plimpton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the play equipment, swings, spray shower, seating, pavements, drainage systems, drinking fountain, fencing and entrance area at Plimpton Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: October 2018

Construction

Start Date: November 2018
Projected Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $3,796,000
Funding Source: Mayoral

Location

Plimpton Playground , Bronx
Edward L. Grant Highway and Plimpton Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/14/2018