Astoria Park Reconstruction

  • Design
    5% complete 
  • Procurement
     
  • Construction
     

This project will reconstruct a portion of Astoria Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date:December 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayor
  • City Council

Location

Astoria Park, Queens
Astoria Park bounded by Shore Boulevard, Ditmars Boulevard, 19th street and Astoria Park South

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project