Almeda Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Almeda Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: May 2019

Construction

Start Date: July 2019
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $6,891,000
Funding Source: Mayoral

Location

Almeda Playground , Queens
Beach Channel Drive between Beach 65th Street and Beach 66th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/18/2019