Clawson Playground Reconstruction Phase I

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the area of Clawson Playground behind PS 50 with new play equipment, safety surfacing, benches and plantings.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,732,000
Funding Sources:
  • Borough President
  • City Council

Location

Clawson Playground , Staten Island
Adelaide Avenue betweeen Elmira Street and Whitehall Street

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/22/2020