Clawson Playground Reconstruction Phase I

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the asphalt yard adjacent to PS 50 and will include new play equipment, safety surfacing, benches and plantings.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: April 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Clawson Playground, Staten Island
Clawson Playground is located adjacent to PS 50, south of Adelaide Avenue and West of Clawson Avenue, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 02/16/2018