Little Bush Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground at Little Bush Park.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $3,253,000
Funding Sources:
  • City Council
  • Mayoral

Location

Nathan Weidenbaum Playground , Queens
Laurel Hill Boulevard between 63rd Street and 64th Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 10/03/2022