Ravenswood Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will reconstruct Ravenswood Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $7,194,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Ravenswood Playground , Queens
21st Avenue between 34th Avenue and 35th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/29/2021