Brookville Park Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    22% complete

This project will reconstruct an entrance to Brookville Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $2,132,000
Funding Source: City Council

Location

Brookville Park , Queens
147th Avenue and Brookville Boulevard

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/05/2020