Brookville Park Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    22% complete

This project will reconstruct an entrance to Brookville Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Adjusted Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,132,000
Funding Source: City Council

Location

Brookville Park , Queens
147th Avenue and Brookville Boulevard

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/14/2020