Sunset Cove Park Boardwalk and Outdoor Classroom Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a wooden boardwalk, outdoor classroom, and pathways in Sunset Cove Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: January 2018
Adjusted Completion Date: April 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Cross Bay Boulevard between West 19th Road and West 22nd Road

Project Staff

Contact NYC Parks about this project

Last updated: 01/19/2019