Flushing Meadows Corona Park Henry Hudson Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Henry Hudson entrance at Flushing Meadows Corona Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $4,512,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
111th Street between 53rd Avenue and 56th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/31/2020