Pulaski Park Sport Courts Reconstruction and Tot Lot Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct the sport courts and construct a tot lot in Pulaski Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: July 2018
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $3,107,000
Funding Sources:
  • Mayoral
  • City Council

Location

Pulaski Park , Bronx
Bruckner Boulevard between Willis Avenue and Brown Place

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/19/2020