Flushing Meadows Corona Park Garage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the Parks Maintenance and Operations garage in Flushing Meadows Corona Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: December 2019
Projected Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $8,078,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
Between Roosevelt Avenue and the Long Island Rail Road yard

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/13/2019