Flushing Meadows Corona Park Garage Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the Flushing Meadows Corona Park Garage Building.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
Located between Roosevelt Avenue and the LIRR, in Flushing Meadows Corona Park, Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/19/2018