Public Place Mall Paving Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Public Place Mall.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: June 2018

Construction

Start Date: April 2019
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $675,000
Funding Source: City Council

Location

Public Place , Brooklyn
Eldert Lane, Liberty Avenue, and Glenmore Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2018