Public Place Mall Paving Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct paving and sidewalks in Public Place Mall. Work will include new bluestone paving, sidewalks, and seating areas.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Public Place, Brooklyn
Bounded by Eldert Lane, Liberty Avenue, and Glenmore Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/16/2018