Public Place Mall Paving Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct paving and sidewalks in Public Place Mall. Work will include new bluestone paving, sidewalks, and seating areas.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Adjusted Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Public Place , Brooklyn
Bounded by Eldert Lane, Liberty Avenue, and Glenmore Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/22/2018