Manhattan Beach Promenade Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the promenade pavements, concrete steps, benches and trees in Manhattan Beach Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline


Start Date: September 2016
Projected Completion Date: September 2017
Completion Date: January 2018


Start Date: January 2018
Projected Completion Date: October 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Between $1 million and $3 million
Funding Source: City Council


Manhattan Beach Park , Brooklyn
Located on Oriental Boulevard between Ocean Avenue and Mackenzie Street.


Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 03/23/2018