Sunset Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct stairs, handrails and landings in Sunset Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $869,000
Funding Source: City Council

Location

Sunset Park , Brooklyn
Near the corner of 5th Avenue and 44th Street, and at 43rd Street and 5th Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/13/2019