Sunset Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    62% complete

This project will reconstruct stairs, handrails and landings in Sunset Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $869,000
Funding Source: City Council

Location

Sunset Park , Brooklyn
Near the corner of 5th Avenue and 44th Street, and at 43rd Street and 5th Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/05/2020