Sunset Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct stairs, handrails and landings in Sunset Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Sunset Park , Brooklyn
Near the corner of 5th Avenue and 44th Street, and at 43rd Street and 5th Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/24/2019