NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Van Cortlandt Park Broadway Entrance Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the entrance to Van Cortlandt Park at Broadway and West 242nd Street.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Source: Mayoral

Location

Van Cortlandt Park, Bronx
BROADWAY AT WEST 242ND STREET, BOROUGH OF THE BRONX

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?