Van Cortlandt Park Broadway Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    85% complete

This project will reconstruct the entrance to Van Cortlandt Park at Broadway and West 242nd Street.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $5,945,000
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
Broadway at West 242nd Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/05/2020