Van Cortlandt Park Broadway Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the entrance to Van Cortlandt Park at Broadway and West 242nd Street.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
BROADWAY AT WEST 242ND STREET, BOROUGH OF THE BRONX

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 09/25/2018