Van Cortlandt Park Broadway Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    31% complete

This project will reconstruct the entrance to Van Cortlandt Park at Broadway and West 242nd Street.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $5,945,000
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
Broadway at West 242nd Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/15/2019