Bridge Park 2 Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the play equipment, swings, and spray shower and construct a new adult fitness area, a multi-purpose synthetic turf field with a performance stage, benches, fences, drainage, water supply and planting at Bridge Park 2.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Private

Location

Bridge Park , Brooklyn
Jay Street, York Street, Bridge Street, Prospect Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/19/2018