Susan Smith McKinney Steward Park Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the play equipment, swings, and spray shower and construct a new adult fitness area, a multi-purpose synthetic turf field with a performance stage, benches, fences, drainage, water supply and planting at Susan Smith McKinney Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
June 2019
Procurement
Start Date: June 2019
Projected Completion Date:
March 2020
Adjusted Completion
Date:
November 2020
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Private
Location
Susan Smith McKinney Steward Park
, Brooklyn
Jay Street, York Street, Bridge Street, Prospect Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/20/2021