Brower Park Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the basketball courts at Brower Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: December 2018
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $692,000
Funding Sources:
  • Borough President
  • City Council

Location

Brower Park , Brooklyn
Brooklyn Avenue and Park Place

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/19/2019