Brower Park Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will Reconstruct the Basketball Courts within Brower Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Borough President
  • City Council

Location

Brower Park , Brooklyn
Brower Park, near the intersection of Brooklyn Avenue and Park Place

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/21/2018