Jackie Robinson Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct stairways, fencing, sidewalks, and entrances in Jackie Robinson Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Construction

Start Date: October 2018
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $4,441,000
Funding Source: Mayoral

Location

Jackie Robinson Park , Manhattan
West 145th Street, West 155th Street, Edgecombe Avenue, Bradhurst Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/15/2018