Jackie Robinson Park Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct stairways, fencing, sidewalks, and entrances in Jackie Robinson Park.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Jackie Robinson Park , Manhattan
Located between 145th Street and 155th Street, and between Edgecombe Avenue and Bradhurst Avenue in Manhattan.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project