Colucci Playground Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct an adult fitness area in Colucci Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Adjusted Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Colucci Playground , Bronx
Wilkins Avenue between Hutchinson River Parkway East and Mayflower Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/02/2018