Colucci Playground Adult Fitness Equipment Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an adult fitness area in Colucci Playground.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: March 2017
Projected Completion Date:
December 2017
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
November 2018
Construction
Start Date: May 2019
Projected Completion Date:
May 2020
Completion
Date:
August 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Colucci Playground
, Bronx
Wilkinson Avenue between Hutchinson River Parkway East and Mayflower Avenue
Project Staff
Project Liaison: Mike Ortiz
Contact NYC Parks
about this project
Last updated: 06/28/2022