Faber Park Active Recreation, Lighting and Seating Area Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct new active recreation areas, paths, seating, lighting and an expanded public gathering area at Faber Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Adjusted Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Faber Pool and Park , Staten Island
2175 Richmond Terrace, between Faber Street and Sharpe Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/19/2019