Linden Park Synthetic Turf Field and Rubberized Track Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the existing synthetic turf field and running track and construct new drinking fountains and sports field spray misters in Linden Park.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Linden Park , Brooklyn
Linden Boulevard and Vermont Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/17/2018