Saul Weprin Playground Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the pavements, seating, fencing and general site work at Saul Weprin Playground Plaza.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Saul Weprin Playground , Queens
Located north of 56th Avenue between 201st Street and 202nd Street.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/13/2018