Queens General Site Work (QG-217M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Lt. Clinton L. Whiting Square, the sidewalk and guide rail along the west side of Harvey Park, and the pathway between Park Lane South at 86th Street and the bandshell in Forest Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $2,068,000
Funding Source: City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/11/2019