Queens General Site Work (QG-217M)

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct pavements, fencing and landscaping at various parks in Queens.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Adjusted Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/25/2019