Flushing Meadows Corona Park World's Fair Marina Reconstruction (Hurricane Sandy)

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the deteriorated fixed piers, floating docks, bulkhead, and related components, including Sandy-damaged elements.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: April 2019
Adjusted Completion Date: April 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Flushing Meadows Corona Park , Queens
Flushing Bay, at 125-00 Northern Boulevard

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/15/2019