Flushing Meadows Corona Park World's Fair Marina Reconstruction (Hurricane Sandy)
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct the deteriorated fixed piers, floating docks, bulkhead, and related components, including Sandy-damaged elements.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: August 2017
Projected Completion Date:
April 2019
Adjusted Completion Date:
April 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Flushing Meadows Corona Park
, Queens
Flushing Bay, at 125-00 Northern Boulevard