Callahan Kelly Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the playground, spray shower, perimeter sidewalks and walls, basketball courts, adult fitness equipment and sitting areas in Callahan Kelly Playground. In addition, this project will include a new skate park and park entrances.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2016
Projected Completion Date: January 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Callahan-Kelly Playground , Brooklyn
Bounded by Fulton and Truxton Streets, Eastern Parkway and Van Sinderen Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/19/2018